KEVOS
ArticlesServicesCase studiesAboutContact
ArticlesServicesCase studiesAboutContact
← ArticlesPlates, Shells, and CylindersEngineering · MechanicalLesson 7/129← PrevNext →
GuidePublished 11 Jul 2026Updated 13 Aug 20268 min readBy Kevin Jogin
On this page

Ask about this page

KEVOS AIPlates, Shells, and Cylinders

KEVOS knowledge first · trusted web sources when needed

Skip to content
KEVOS® Knowledge Library · Engineering → Mechanical Engineering

Engineering / Mechanical Engineering

Plates, Shells, and Cylinders

Pressure pushes outward; the wall answers with hoop tension. Thin walls answer uniformly, thick walls pile the stress at the bore, and flat covers bend — three regimes, three formulas, one page.

  • Reading time · 3 min
  • 6 sections
  • Hoop stress is double longitudinal
  • Three walls sized in mm
p σ_h σ_h wall t every diametral cut must carry p × d per unit length — hence σ_h = pd/2t
Doc №KL-ENG-MECH-014
SectionEngineering → Mechanical Engineering
Sheet1 of 1
DrawnKEVOS®
Date2026-07-11

In this reference

  1. Thin cylinders
  2. Thin spheres
  3. Thin or thick?
  4. Thick cylinders — Lamé
  5. Flat circular plates
  6. Quick reference

§1Thin cylinders

Cut the shell in imagination and balance what the pressure pushes against what the wall pulls. Two cuts, two stresses — and the hoop one is double.

hoop σ_h = p rt = p d2t   longitudinal σ_l = p r2t

Hoop governs — which is why pressurised tubes split along their length, never around it, and why a longitudinal weld carries twice the duty of a circumferential one (weld efficiency enters as a divisor on the allowable stress).

Example 1 — an air receiver wall

Ø600 mm receiver at 1.0 MPa, allowable 80 MPa: t = pr/σ = 1.0 × 300/80 = 3.75 mm; adding a 1 mm corrosion allowance and rounding, t = 5 mm, running at a comfortable 60 MPa hoop. Pressure equipment is code territory — the mechanics above is the skeleton the codes clothe with rules, allowances and inspection.

Contents

§2Thin spheres

σ = p r2t — every direction at once

A sphere carries the same pressure at half the cylinder’s wall (the receiver above would need only 1.9 mm) — the shape’s whole surface works in the efficient longitudinal mode. That efficiency is why gas storage trends spherical and why cylinder ends are dished rather than flat: a hemispherical head is a sphere doing a lid’s job.

Contents

§3Thin or thick?

The thin formulas assume the stress is uniform through the wall. That holds while the wall is a small fraction of the diameter.

Working rule: treat the shell as thin while t < d/20. Beyond that the inner fibres carry visibly more than the outer — the thin formula under-reports the bore stress and Lamé takes over. Hydraulic cylinders, gun-drill bushes and high-pressure fittings live on the thick side almost by definition.

Contents

§4Thick cylinders — Lamé

In a thick wall the hoop stress varies through the thickness, peaking at the bore. For internal pressure p on radii rᵢ (bore) and r₀ (outside):

σ_h,max (at bore) = p × r₀² + rᵢ²r₀² − rᵢ²   solved for size: r₀ = rᵢ (σ + p)/(σ − p)
Example 2 — a hydraulic cylinder barrel

Bore Ø80 mm at 35 MPa, allowable 110 MPa: r₀ = 40√(145/75) = 55.6 mm → wall 15.6 → use 16 mm (r₀ = 56: bore stress 107.9 MPa ✓). Note the formula’s warning: as p approaches σ the required r₀ runs to infinity — past that point no amount of wall helps, and the answers are stronger material, autofrettage or compound (shrink-fitted) construction.

Contents

§5Flat circular plates

A flat cover doesn’t stretch like a shell — it bends like a plate, and its stress grows with the square of the radius-to-thickness ratio.

Uniform pressure p, radius r, ν = 0.3 edges fixed: σ_max = 0.75 p (r/t)² (at the rim)   simply supported: σ_max ≈ 1.24 p (r/t)² (at the centre)
Example 3 — a bolted flat cover

Ø300 mm opening at 0.5 MPa, edges effectively fixed by the bolted flange, allowable 90 MPa: (r/t)² = 90/(0.75 × 0.5) = 240, so r/t = 15.5 and t = 150/15.5 = 9.7 → use 10 mm. A flat lid this size needs 10 mm where a dished end would need 2 — flatness is bought with thickness, which is the whole argument for dished ends.

Contents

§6Quick reference

The working core of the page on one card rack.

Thin cylinder

σ_h = pd/2t · σ_l = pd/4t

hoop governs, ×2

Thin sphere

σ = pd/4t

half the cylinder’s wall

Regime

thin while t < d/20

Thick (Lamé)

σ_bore = p(r₀²+rᵢ²)/(r₀²−rᵢ²)

r₀ = rᵢ√((σ+p)/(σ−p))

Flat plate

fixed: 0.75 p(r/t)²

supported: ≈1.24 p(r/t)²

Contents

Handbook application: from concept to controlled practice

Purpose. This expanded section turns the original page into a practical handbook. It preserves the supplied material and adds a repeatable way to apply, check and review Plates, Shells, and Cylinders. It does not replace a contract, legislation, a controlled standard, competent engineering judgement or specialist advice.

The operating aim is to carry the subject from function and assumptions through design evidence, verification and controlled release. Read the original explanation first, then use the workflow and checks below to convert knowledge into evidence.

Apply Plates, Shells, and Cylinders by beginning with the duty, not the component or software command. Convert the key ideas—thin, plates, cylinders, spheres, lamé—into measurable requirements and interfaces. Record operating and non-operating environments, duty cycle, expected life, loads, energy sources, human interaction and reasonably foreseeable abnormal conditions. When a value is not a project requirement or verified supplier datum, identify it as an assumption or illustrative value.

Create a calculation and evidence trail that another competent person can audit. Every input should carry a source, unit, revision and uncertainty or tolerance where relevant. Every model should state its boundary conditions and limitations. Keep nominal capacity separate from design capacity, and keep verification margin separate from an arbitrary safety factor. If a code or standard governs the work, confirm the applicable edition and contractual status rather than copying a number from a secondary summary.

Design for manufacture, assembly, inspection, operation and maintenance at the same time. A technically valid geometry can still fail because it cannot be fixtured, measured, cleaned, guarded, reached or replaced. Review process capability, datum or reference strategy, tolerance accumulation, access, error-proofing and changeover. Where people interact with plant, apply the hierarchy of controls and consult those who will operate, clean, maintain and recover the equipment.

Plan verification before release. Define the characteristic, method, equipment, sample or test condition, acceptance criterion, record and responsible person. Validation then asks a different question: whether the resulting system is effective and suitable in the intended use context. A passed drawing check or analysis does not by itself validate usability, maintainability or production performance.

Step-by-step operating method

  1. Define the duty. Capture the required function, interfaces, operating environment, life, loads and unacceptable outcomes.
  2. Establish the model. Identify governing principles, units, material or process data, assumptions and uncertainty.
  3. Develop alternatives. Compare feasible concepts against performance, manufacturability, safety, maintainability and cost.
  4. Verify the design. Use analysis, test, inspection or demonstration with acceptance criteria defined before execution.
  5. Release and learn. Baseline the design, control changes, retain evidence and feed operating results into the next revision.

Illustrative design review record

Illustrative values only. Build a one-page record with the required function, input sources, assumptions, governing load or process condition, failure consequences, selected concept, verification method and acceptance criterion. Mark every numerical input as project requirement, verified supplier data, measured value, calculation output or assumption. Review the weakest evidence first. If an assumption can change safety, compliance, interchangeability or capacity, it must be resolved before release rather than buried in a calculation note.

Evidence classQuestionRelease expectation
RequirementWhat must the design do and under which conditions?Approved and traceable
InputWhere did the load, property, tolerance or process limit come from?Source, unit and revision recorded
AnalysisWhich model and assumptions connect input to result?Checkable calculation or simulation
VerificationHow will conformity be demonstrated?Method and acceptance criterion agreed
ValidationWill the solution work for intended users and conditions?Representative use evidence

Common failure modes and recovery actions

1. Watch for

Starting detailed design before interfaces and operating limits are agreed.

Recovery: Return to the governing definition or requirement and restate the decision in one sentence.

2. Watch for

Using catalogue or typical values as though they were certified project inputs.

Recovery: Separate evidence from assumption, assign an owner and set a date for validation.

3. Watch for

Checking nominal performance while ignoring tolerances, degradation and foreseeable misuse.

Recovery: Run a small counterexample, boundary test, pilot or independent check before proceeding.

4. Watch for

Confusing verification of requirements with validation of user need.

Recovery: Record the consequence, decision and rationale, then update the controlled baseline.

5. Watch for

Releasing drawings or procedures without configuration, inspection and change controls.

Recovery: Escalate when the issue affects safety, compliance, acceptance, material value or an agreed tolerance.

Review checklist

  • What function and failure consequence govern this decision?
  • Which inputs are measured, specified, assumed or illustrative?
  • How will conformity be demonstrated and recorded?
  • What change would invalidate the current evidence?
  • Are mandatory requirements distinguished from recommendations and illustrative values?
  • Are sources, assumptions, units, dates and versions recorded closely enough to reproduce the decision?
  • Have safety, legal, ethical, stakeholder and operational consequences been considered at the appropriate level?
  • Is there a named owner and a trigger for review, escalation, change or retirement?

Questions for deeper application

What is the most important distinction a practitioner must preserve when applying Plates, Shells, and Cylinders?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Which assumption about thin would change the result most if it proved false?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

What evidence would allow an independent reviewer to reproduce or challenge the conclusion?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Which boundary, exception or failure case has not yet been tested?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

What must be handed over, monitored or reviewed after the immediate work is complete?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Authoritative references and use notes

The sources below were selected as institutional or primary guidance for the broader practice. They support the handbook method; they do not imply that every statement or clause in a source applies to every project. Confirm the current edition, jurisdiction, contract and application before treating any requirement as mandatory.

  • NASA Systems Engineering Handbook — NASA. Used for requirements, design, verification, validation and technical management. Accessed 2026-08-13.
  • Identify, assess and control hazards — Safe Work Australia. Used for hazard identification, risk assessment, controls and review. Accessed 2026-08-13.

KEVOS® Knowledge Library · Engineering → Mechanical Engineering · Original KEVOS® synthesis — written, computed and drawn for this page. Built 11 July 2026.

Continue learning

NEXT LESSON →SOLIDWORKS Deployment Methods & System Options GovernanceGuide · MechanicalThe SOLIDWORKS Administrative ImageGuide · MechanicalSOLIDWORKS Licence Models & Entitlement PlanningGuide · MechanicalSOLIDWORKS Operating Environment ConfigurationGuide · Mechanical
KEVOS · Engineering, manufacturing and project improvement
ArticlesServicesCase studiesAboutContact
© 2026 KEVOS®