KEVOS
ArticlesServicesCase studiesAboutContact
ArticlesServicesCase studiesAboutContact
← ArticlesZoo Relocation Project Initiation Case StudyProject Delivery · Principles of Project ManagementLesson 18/58← PrevNext →
GuidePublished 13 Aug 20269 min readBy Kevin Joginproject managementproject deliveryprinciples of project managementmedium
On this page

Ask about this page

KEVOS AIZoo Relocation Project Initiation Case Study

KEVOS knowledge first · trusted web sources when needed

Home/ Project Delivery/ Principles of Project Management

KEVOS® Project Delivery Handbook

Zoo Relocation Project Initiation Case Study

A practical KEVOS handbook guide to Zoo Relocation Project Initiation Case Study, with applied methods, controls, examples and common pitfalls.

9 min read1,785 words Guide 18 of 57Reviewed 2026-08-13
In this handbook article
  1. The Scenario
  2. Applying the Project Charter Framework
  3. 1. Project Objectives
  4. 2. Scope Statement
  5. 3. Exclusions
  6. 4. Assumptions
  7. 5. Constraints
  8. 6. Key Risks
  9. 7. Project Organisation
  10. Applying the Stakeholder Identification Framework
  11. Identified Stakeholders
  12. Power/Interest Classification
  13. Knowledge Checks
  14. Key Takeaways from the Case

Source and edition context

Source basis: This handbook article is adapted from the supplied file(s): 19. The Zoo Project - A Case Study in Project Initiation.md.

Interpretation rule: Named scenarios, schedules, percentages, monetary values and thresholds are source examples or illustrative proposals unless an identified authority, contract or approved baseline makes them mandatory.

Lifecycle Phase 1 — Companion Case Study

What happens when a nearly 100-year-old zoo — profitable, beloved by the community, home to hundreds of animals and dozens of staff — receives a memo from corporate headquarters saying it must close within 10 months?

This case study walks through the Fairfield Zoo closure project from the perspective of project initiation. It applies the concepts from our Masterclass articles on the The Project Charter and Identifying Project Stakeholders to a scenario that is messy, politically charged, and operationally complex — exactly the kind of project where getting Phase 1 right determines everything.


The Scenario

The Organisation: Fairways Leisure & Tourism Group — a family-owned conglomerate spanning theme parks, budget resorts, and the Fairfield Zoo. Mark Palmer, great-grandson of the founder, has been appointed Chairman of the Board.

The Strategic Decision: A market research study has concluded that eco-tourism targeting the premium segment is the most profitable direction for the Group. This triggers a corporate restructure: theme parks and budget resorts will be closed or sold. The Fairfield Zoo — though still meeting revenue targets — occupies prime real estate that can generate significant capital for the restructure.

The Directive: Close the Zoo. Prepare the site for handover to the Nirvana Development Company for housing construction. Retain only the heritage-listed Administration building and identified significant trees. Relocate all animals. Redeploy all staff.

The Timeline: 10 months from project commencement.

The Stakes: Success means promotions and increased salaries for the Zoo Director and departmental heads. Failure means award termination payments only.


Applying the Project Charter Framework

The memo from the Chief Executive explicitly requests a Project Charter. Let's work through each section using the information provided.

1. Project Objectives

Using the SMART framework, the Zoo Project's objectives can be framed as:

SMART Criteria Objective
Specific Close and dismantle the Fairfield Zoo in its entirety
Measurable Zero animal fatalities during relocation; 100% staff redeployment within the Group
Action-oriented Demolish all structures except heritage-listed buildings; clear site for developer handover
Realistic Operate within the existing $6M asset base; project must aim to return a profit
Time-limited Complete within 10 months of commencement

2. Scope Statement

The scope of the Fairfield Zoo Closure Project encompasses three major deliverables:

  1. Complete closure and dismantling of the Zoo in its entirety
  2. Redeployment of all staff to alternative positions within the Fairways Leisure & Tourism Group
  3. Site clearance of all buildings and structures — excluding heritage-listed items — so that the Nirvana Development Company may commence construction of a housing development
Process and relationship map
Fairfield Zoo — Closure Project
Work Stream 1 — Animal Relocation
Work Stream 2 — Staff Redeployment
Work Stream 3 — Site Demolition — & Clearance
Work Stream 4 — Administration — & Finance
All animals safely — relocated to accredited — facilities
All staff placed in — alternative roles within — the Group
Site cleared and — ready for developer — handover
Project returns — a profit; assets — disposed of
Relationship details
FromRelationshipTo
Fairfield Zoo — Closure Projectleads toWork Stream 1 — Animal Relocation
Fairfield Zoo — Closure Projectleads toWork Stream 2 — Staff Redeployment
Fairfield Zoo — Closure Projectleads toWork Stream 3 — Site Demolition — & Clearance
Fairfield Zoo — Closure Projectleads toWork Stream 4 — Administration — & Finance
Work Stream 1 — Animal Relocationleads toAll animals safely — relocated to accredited — facilities
Work Stream 2 — Staff Redeploymentleads toAll staff placed in — alternative roles within — the Group
Work Stream 3 — Site Demolition — & Clearanceleads toSite cleared and — ready for developer — handover
Work Stream 4 — Administration — & Financeleads toProject returns — a profit; assets — disposed of

3. Exclusions

Based on the case material, the following should be explicitly excluded:

  • The sale of the land itself — income from the future land sale is not available to be applied to this project
  • Construction of the housing development — that is the Nirvana Development Company's scope
  • Heritage restoration of the Administration building — the building must be retained, but restoration is not part of this project
  • Ongoing management of the eco-tourism restructure across the wider Group

4. Assumptions

Key assumptions that would need to be documented:

  • Current zoo staff will cooperate with the closure and redeployment process
  • Suitable positions exist within the Group for all current staff members
  • Accredited animal facilities will accept the Zoo's animals within the project timeline
  • The heritage-listed Administration building does not require structural remediation before handover
  • Specialist resources (veterinarians, demolition contractors, transport providers, HR counsellors) can be sourced within the project budget
  • The Nirvana Development Company's timeline aligns with the 10-month delivery window

Knowledge Check: How many of these assumptions carry significant risk? (Answer: All of them. Every assumption is a risk in disguise.)

5. Constraints

The project operates under several hard constraints:

Constraint Detail
Time 10 months — non-negotiable deadline set by the Board
Budget Zoo assets currently valued at $6M; land sale income is not available to fund the project
Profitability The project must aim to return a profit — it cannot be a net cost to the organisation
Heritage The heritage-listed Administration building and significant trees must be retained
Staffing Delivery will be carried out principally by current staff
Ethical Animals must be relocated without harm
Regulatory Heritage register requirements; animal welfare legislation; employment law

6. Key Risks

The case study identifies five significant risks:

Process and relationship map
Community Backlash — Related to site re-use
Animal Loss — Due to lack of prep time, — age, physical condition
Staff Placement Failure — Inability to place staff — satisfactorily
Resource Overload — Overloading due to — wider restructure
Opportunity Cost — Cost of NOT proceeding — with closure
Impact: Reputational — damage, legal challenges, — delays
Impact: Ethical failure, — media crisis, regulatory — action
Impact: Industrial — relations issues, — legal exposure
Impact: Schedule — slippage, quality — compromise
Impact: Continued — maintenance costs, — missed restructure — window
Relationship details
FromRelationshipTo
Community Backlash — Related to site re-useleads toImpact: Reputational — damage, legal challenges, — delays
Animal Loss — Due to lack of prep time, — age, physical conditionleads toImpact: Ethical failure, — media crisis, regulatory — action
Staff Placement Failure — Inability to place staff — satisfactorilyleads toImpact: Industrial — relations issues, — legal exposure
Resource Overload — Overloading due to — wider restructureleads toImpact: Schedule — slippage, quality — compromise
Opportunity Cost — Cost of NOT proceeding — with closureleads toImpact: Continued — maintenance costs, — missed restructure — window

7. Project Organisation

The case study defines the following organisational structure:

  • Project Sponsor: Chief Executive, Fairways Leisure & Tourism Group
  • External Project Manager: Appointed from an external consultancy firm
  • Core Project Team:
    • Director, Fairfield Zoo
    • General Manager, Administration & Finance
    • General Manager, Animal Management
    • General Manager, Horticulture and Maintenance
  • Specialist Resources (as required): Veterinarians, demolition contractors, transport providers, HR counsellors
Process and relationship map
Board of Directors — (Mark Palmer, Chairman)
Chief Executive — (Project Sponsor)
External Project Manager — (Consultancy Firm)
Director, — Fairfield Zoo
GM Administration — & Finance
GM Animal — Management
GM Horticulture — & Maintenance
Veterinary — Specialists
Demolition — Contractors
Transport — Providers
HR — Counsellors
Relationship details
FromRelationshipTo
Board of Directors — (Mark Palmer, Chairman)leads toChief Executive — (Project Sponsor)
Chief Executive — (Project Sponsor)leads toExternal Project Manager — (Consultancy Firm)
External Project Manager — (Consultancy Firm)leads toDirector, — Fairfield Zoo
External Project Manager — (Consultancy Firm)leads toGM Administration — & Finance
External Project Manager — (Consultancy Firm)leads toGM Animal — Management
External Project Manager — (Consultancy Firm)leads toGM Horticulture — & Maintenance
External Project Manager — (Consultancy Firm)leads toVeterinary — Specialists
External Project Manager — (Consultancy Firm)leads toDemolition — Contractors
External Project Manager — (Consultancy Firm)leads toTransport — Providers
External Project Manager — (Consultancy Firm)leads toHR — Counsellors

Applying the Stakeholder Identification Framework

Now let's apply the stakeholder identification process from our companion article. Who are the stakeholders in the Zoo Project, and where do they sit on the Power/Interest Grid?

Identified Stakeholders

Stakeholder Interest Disposition Power Interest Level
Mark Palmer (Chairman) Corporate restructure success Supportive High Medium
Chief Executive (Sponsor) Project delivery, cost recovery Supportive High High
Zoo Director Career continuity, animal welfare Mixed Medium High
GM Administration & Finance Budget management, staff Mixed Medium High
GM Animal Management Animal welfare, professional reputation Mixed Medium High
GM Horticulture & Maintenance Site operations, job security Mixed Medium High
Zoo Staff (general) Employment, uncertainty Resistant Low High
Nirvana Development Company Timely site handover Supportive Medium Medium
Local Community Loss of amenity, heritage Resistant Medium High
Local Council / Heritage Body Heritage compliance Neutral High Medium
Animal Welfare Organisations Humane treatment of animals Neutral/Resistant Medium High
Media Public interest story Neutral Medium High
Unions / Employee Representatives Staff rights, redeployment terms Resistant Medium High

Power/Interest Classification

Zoo Project — Power/Interest Grid

Low Interest --> High Interest · Low Power --> High Power

Keep Satisfied

  • Heritage Body

Manage Closely

  • Chief Executive
  • Chairman Palmer
  • Zoo Director
  • Nirvana Dev Co
  • Unions

Monitor

  • Classify relevant stakeholders here

Keep Informed

  • Local Community
  • Zoo Staff
  • Media
  • Animal Welfare Orgs

Analysis: The Chief Executive and Chairman occupy the "Manage Closely" quadrant. The Zoo Director sits at the boundary — high interest, medium power — making their engagement critical. The local community has high interest but limited formal power, placing them in the "Keep Informed" zone — but their capacity to generate media attention and political pressure means they should be treated with more care than the grid alone suggests.


Knowledge Checks

Test your understanding of the concepts applied in this case study.

Question 1: The case memo states that the project "must aim to return a profit." Is this an objective, a constraint, or both? Why does the distinction matter?

Question 2: The Zoo Director's disposition is listed as "Mixed." What factors might drive them toward support versus resistance? How would you manage this stakeholder?

Question 3: The local community is classified as "Keep Informed" on the Power/Interest Grid. Under what circumstances could their position shift to "Manage Closely"?

Question 4: Identify three assumptions in this case study that, if proven false, would require a fundamental change to the project plan.

Question 5: The project will be managed by an external consultancy firm, while the core team consists of internal Zoo staff. What governance risks does this arrangement create, and how would you address them in the Project Organisation section of the Charter?


Key Takeaways from the Case

  • The Zoo Project demonstrates that emotionally charged projects with community impact require exceptional stakeholder management, not just technical project management
  • The constraints are severe: fixed timeline, self-funding requirement, ethical obligations around animal welfare, heritage compliance, and employment law
  • Every assumption in this project carries material risk — the Charter must explicitly acknowledge this and pair each assumption with a contingency
  • The mixed disposition of the core project team (who face personal uncertainty about their own futures) is a governance risk that must be addressed through clear communication and incentive alignment
  • Stakeholder classification is a starting point, not a conclusion — stakeholders whose formal power is low but whose capacity to generate reputational or political pressure is high must be managed with a level of care that exceeds what the grid alone suggests

This case study is a companion to the Masterclass articles on The Project Charter and Identifying Project Stakeholders.

Continue learning

Project InitiationIdentifying Project Stakeholders9 min readLifecycle HandbookStarting the Project7 min readProject InitiationThe Project Charter8 min readPostgraduate Project Management StudyHow to Score a High Distinction on a Postgraduate Project Management Group Report28 min read

Prepared for the KEVOS® Knowledge Library. Apply the governing contract, approved project method and current standards to live work.

Continue learning

Identifying Project StakeholdersGuide · Principles of Project ManagementNEXT LESSON →Mastering the Project Management PlanGuide · Principles of Project ManagementThe Project CharterGuide · Principles of Project ManagementMastering the Work Breakdown StructureGuide · Principles of Project Management
KEVOS · Engineering, manufacturing and project improvement
ArticlesServicesCase studiesAboutContact
© 2026 KEVOS®