KEVOS® Project Delivery Handbook
Zoo Relocation Project—Part 3: WBS, Schedule and Critical Path
18 months, a zero-casualty mandate, a reuse-enclosures instruction, and a staged-closure strategy that overlaps planning with execution.
In this handbook article
- The Challenge
- The PM Framework Applied
- Step 1: Scope Baseline — Scope Statement → WBS → WBS Dictionary
- Step 2: Build the WBS
- Step 3: Decompose to work package level
- Step 4: Sequence into a network diagram
- Step 5: Calculate the critical path
- Step 6: Fast-track or crash where required
- Step 7: Baseline the schedule
- The Result
- The Pitfalls
- Knowledge Check
- Key Takeaways
- References
18 months, a zero-casualty mandate, a reuse-enclosures instruction, and a staged-closure strategy that overlaps planning with execution. Part 3 builds the WBS, network diagram, and critical path.
Series recap. Parts 1–2 produced the Charter, Stakeholder Engagement Plan, and Communications Plan. Part 3 enters the technical heart of project planning: scope decomposition and schedule construction.
The Challenge
The CEO's letter contains requirements that, on paper, do not fit in the available time:
| Requirement | Time Implication |
|---|---|
| Sell current site within 12 months | Planning and site acquisition must run in parallel with the sale |
| Operational within 18 months of public closure | Closure cannot happen until the new site can re-house animals |
| Retain and reuse existing enclosures | Each exhibit has a dismantle → transport → re-erect cycle |
| Zero-percent casualty rate | Animal transport cannot be rushed or paralleled aggressively |
| Staged relocation permitted | Some flexibility — but only if the new site is partially operational |
| Full staff retention | Workforce must be productively employed throughout |
These requirements are not all satisfiable under a naive waterfall schedule. The project must be broken into overlapping workstreams — fast-tracking in PMBOK language, phased delivery in heavy-engineering practice.
The PM Framework Applied
Step 1: Scope Baseline — Scope Statement → WBS → WBS Dictionary
PMBOK's Scope Management (Chapter 5) makes the sequencing explicit. The scope baseline consists of three artefacts:
- Project Scope Statement — a prose document of scope, deliverables, acceptance criteria, exclusions, constraints, and assumptions.
- WBS — hierarchical decomposition of scope into deliverables and work packages.
- WBS Dictionary — detailed information per WBS element.
The scope statement must name what is out of scope: ongoing operation of the new site beyond opening, long-term animal husbandry training programs, capital fundraising beyond sale proceeds, legal disputes from the site handover. Declaring exclusions is how the PM prevents the project absorbing tasks that belong to business-as-usual.
Step 2: Build the WBS
A WBS decomposes project deliverables into progressively smaller components until each bottom-level element (a work package) is small enough to be estimated, assigned, and tracked. The 8/80 rule: no work package under 8 hours or over 80 hours.
Relationship details
| From | Relationship | To |
|---|---|---|
| 1.0 Zoo Relocation Project | leads to | 1.1 Project Management |
| 1.0 Zoo Relocation Project | leads to | 1.2 Old Site Sale |
| 1.0 Zoo Relocation Project | leads to | 1.3 New Site Acquisition |
| 1.0 Zoo Relocation Project | leads to | 1.4 Design & Construction |
| 1.0 Zoo Relocation Project | leads to | 1.5 Salvage & Asset Transfer |
| 1.0 Zoo Relocation Project | leads to | 1.6 Animal Relocation |
| 1.0 Zoo Relocation Project | leads to | 1.7 Staff Transition |
| 1.0 Zoo Relocation Project | leads to | 1.8 Opening & Commissioning |
| 1.0 Zoo Relocation Project | leads to | 1.9 Project Closure |
| 1.1 Project Management | leads to | 1.1.1 Planning & Control |
| 1.1 Project Management | leads to | 1.1.2 Stakeholder & Comms |
| 1.1 Project Management | leads to | 1.1.3 Risk Management |
| 1.1 Project Management | leads to | 1.1.4 Governance Reporting |
| 1.6 Animal Relocation | leads to | 1.6.1 Welfare Protocols |
| 1.6 Animal Relocation | leads to | 1.6.2 Transport Procurement |
| 1.6 Animal Relocation | leads to | 1.6.3 Regulatory Approvals |
| 1.6 Animal Relocation | leads to | 1.6.4 Staged Species Moves |
| 1.6 Animal Relocation | leads to | 1.6.5 Quarantine & Monitoring |
Two deliberate choices: Project Management (1.1) is itself a WBS element — PM activities consume real resources and must be visible in the WBS. Animal Relocation (1.6) is a top-level element — on a project where welfare is the dominant quality constraint, hiding it inside "Operations" is how zero-casualty commitments become 98% casualty rates.
Step 3: Decompose to work package level
Taking branch 1.6:
| WBS Code | Work Package | Effort (hrs) | Responsible |
|---|---|---|---|
| 1.6.1.1 | Welfare protocols — mammals | 40 | Senior Curator (Mammals) |
| 1.6.1.2 | Welfare protocols — reptiles | 32 | Senior Curator (Herpetology) |
| 1.6.1.3 | Welfare protocols — birds | 32 | Senior Curator (Avian) |
| 1.6.1.4 | Welfare protocols — aquatic | 48 | Senior Curator (Aquatic) |
| 1.6.1.5 | Independent vet review | 24 | External Vet |
| 1.6.2.1 | Specialist transport RFP | 24 | Procurement |
| 1.6.2.2 | Transport tender evaluation | 16 | Procurement + Curators |
| 1.6.3.1 | State wildlife permits | 40 | PM + Legal |
Each row passes 8/80, has a single named responsible party, and has a measurable completion criterion.
Step 4: Sequence into a network diagram
The WBS says what. It says nothing about when. Scheduling begins by identifying dependencies. The four dependency types from PMBOK are Finish-to-Start (most common), Start-to-Start, Finish-to-Finish, and Start-to-Finish (rare).
Relationship details
| From | Relationship | To |
|---|---|---|
| Start | leads to | Charter Signed |
| Charter Signed | leads to | Site Selection |
| Charter Signed | leads to | Old Site Sale |
| Site Selection | leads to | Lease Signed |
| Lease Signed | leads to | Permits |
| Lease Signed | leads to | Design |
| Old Site Sale | leads to | Construction |
| Design | leads to | Construction |
| Salvage | leads to | Construction |
| Permits | leads to | Stage 1 Move |
| Construction | leads to | Stage 1 Move |
| Charter Signed | leads to | Staff Transition |
| Stage 1 Move | leads to | Public Closure |
| Public Closure | leads to | Stage 2 Move |
| Stage 2 Move | leads to | Commissioning |
| Staff Transition | leads to | Commissioning |
| Commissioning | leads to | Opening |
| Opening | leads to | End |
Red nodes are the critical path — the longest chain of dependent activities, which determines minimum project duration. A one-day delay to any critical-path activity delays the project by one day.
Step 5: Calculate the critical path
Definition — Critical Path. The sequence of activities that determines the minimum project duration. Critical-path activities have zero total float.
Formally, via forward and backward passes:
For large projects the arithmetic is done by scheduling software (Primavera P6, MS Project). What the PM must understand is the implication: critical-path activities demand disproportionate management attention, and adding resources to non-critical activities is usually a waste of money.
Step 6: Fast-track or crash where required
- Fast-tracking — overlapping sequential activities. Costs nothing but increases rework risk.
- Crashing — adding resources to critical-path activities. Costs money, yields diminishing returns.
For the Zoo, fast-tracking might mean beginning salvage of low-risk assets before public closure. Crashing might mean running two construction crews in parallel. Both decisions must be logged against risk.
Step 7: Baseline the schedule
| Workstream | Activity | Type | Timing / dependency / duration |
|---|---|---|---|
| Initiation | Charter & Stakeholder | Activity | done · init · 2025-01-01 · 30d |
| Finance & Site | Old Site Sale | Activity | active · sale · 2025-01-15 · 330d |
| Finance & Site | New Site Selection | Activity | active · site · 2025-02-01 · 90d |
| Finance & Site | Lease Execution | Milestone | milestone · lease · after site · 0d |
| Finance & Site | Regulatory Permits | Activity | crit · perm · after lease · 120d |
| Design & Build | New Site Design | Activity | crit · des · after lease · 90d |
| Design & Build | Construction Phase 1 | Activity | crit · b1 · after des · 150d |
| Design & Build | Construction Phase 2 | Activity | crit · b2 · after b1 · 120d |
| Animal Relocation | Welfare Protocols | Activity | wp · 2025-03-01 · 90d |
| Animal Relocation | Stage 1 Moves | Activity | s1 · after b1 · 60d |
| Animal Relocation | Public Closure | Milestone | milestone · closure · after s1 · 0d |
| Animal Relocation | Stage 2 Moves | Activity | crit · s2 · after closure · 120d |
| Animal Relocation | Quarantine | Activity | quar · after s2 · 60d |
| Commissioning | Commissioning | Activity | crit · comm · after quar · 60d |
| Commissioning | Public Opening | Milestone | milestone · open · after comm · 0d |
Relationship details
| From | Relationship | To |
|---|---|---|
| 1.0 Project | leads to | 1.1 Design |
| 1.0 Project | leads to | 1.2 Procurement |
| 1.0 Project | leads to | 1.3 Build |
| 1.0 Project | leads to | 1.4 Test |
| Design Task | leads to | Procurement Task |
| Procurement Task | leads to | Build Task |
| Build Task | leads to | Test Task |
| 1.1 Design | leads to | Design Task |
| Design Task | leads to | link |
| 1.2 Procurement | leads to | Procurement Task |
| Procurement Task | leads to | link |
| 1.3 Build | leads to | Build Task |
| Build Task | leads to | link |
| 1.4 Test | leads to | Test Task |
| Test Task | leads to | link |
The Result
Four additional controlled artefacts: Scope Statement, WBS, WBS Dictionary, Baselined Project Schedule. Together with the charter and stakeholder plan, these constitute the performance measurement baseline for scope and schedule.
The Pitfalls
- Skipping the scope statement. Leaves the WBS with no textual anchor.
- Decomposing by department rather than deliverable. A WBS organised by "Engineering, HR, Finance" is an org chart, not a WBS.
- Omitting project management from the WBS. PM is work; work must be in the WBS.
- Wrong work package sizing. Over 80 hours cannot be estimated accurately; under 8 hours generates tracking overhead exceeding its value.
- Confusing the WBS with the schedule. The WBS has no time dimension.
- Fast-tracking without risk analysis. Overlapping previously sequential activities always increases risk.
- Treating the baseline as unchangeable. The baseline is the reference for measuring change, not a prohibition against it.
Knowledge Check
- The site sale takes 14 months instead of 12. Which downstream activities are affected, and does the critical path change?
- The lead transport contractor goes into administration two weeks before Stage 2. Which work packages are affected, and what are your options?
- During the forward pass you discover construction has 45 days of float but the permit activity has 0. The construction manager asks for an additional crew. How do you respond?
Key Takeaways
- The scope baseline comprises the Scope Statement, WBS, and WBS Dictionary — all three required.
- The WBS decomposes into deliverables, not activities.
- Work packages must obey the 8/80 rule.
- Project management itself is a WBS element.
- The critical path is the longest chain of dependent activities through the network.
- Schedule compression is achieved through fast-tracking or crashing — both carry risk implications.
References
- Project Management Institute 2017, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 6th edn, PMI, Newtown Square, PA.
- Kerzner, H 2017, Project Management: A Systems Approach, 12th edn, Wiley, Hoboken, NJ.
- Burke, R 2013, Project Management: Planning and Control Techniques, 5th edn, Wiley, Chichester.
- Lewis, JP 2011, Project Planning, Scheduling and Control, 5th edn, McGraw-Hill, New York.
- University of South Australia 2015, MPM411 Zoo Relocation Project Brief, UniSA, Adelaide.