Zoo Relocation Project—Part 1: From CEO Letter to Signed Charter
Series note. A practical KEVOS handbook for project delivery teams.
In this handbook article
- The Challenge
- The PM Framework Applied
- Step 1: Decompose the brief into SMART objectives
- Step 2: Log assumptions and constraints explicitly
- Step 3: Identify stakeholders before drafting authority levels
- Step 4: Draft the Charter
- Step 5: Secure formal authorisation
- The Result
- The Pitfalls
- Knowledge Check
- Key Takeaways
- References
Series note. This is Part 1 of a six-part Format C case study walkthrough applying the PMBOK lifecycle to the UniSA Zoo Relocation Project, a fictional but instructively-constrained brief used in MPM411. Each article tackles a different lifecycle phase using the same source material.
The Challenge
You have just been appointed Project Manager. Your only briefing is a one-page letter from Carlos Elliott, CEO of the Zoo. The letter is simultaneously generous — you may appoint your own team, you report directly to the board, staged closure is pre-authorised — and terrifying, because every paragraph contains a constraint that would already be a tough project on its own.
Let us audit what the CEO has actually asked for:
| # | CEO Statement | PM Translation |
|---|---|---|
| 1 | "Generate $20 million profit" | Hard financial success criterion |
| 2 | "Sale of current site finalised within 12 months" | Funding-gate deadline |
| 3 | "Operational within 18 months of public closure" | Schedule constraint from a floating trigger |
| 4 | "Zero-percent casualty rate" | Quality-as-constraint |
| 5 | "Long-term survival a critical success factor" | Benefits-realisation criterion |
| 6 | "Maximum staff retention" | HR/stakeholder constraint |
| 7 | "Retain and reuse existing enclosures" | Scope-cost constraint opposing the schedule |
| 8 | "Fortnightly formal report" | Governance mandate |
| 9 | "Staged relocation" permitted | Delivery strategy hint |
| 10 | "Government grant sustains full closure" | Financial assumption to be quantified |
Ten implicit requirements buried in roughly 400 words of corporate prose. This is entirely typical — in heavy-engineering and defence environments, a Tier-1 prime receiving a one-page Statement of Need does exactly this kind of forensic decomposition as its first initiation activity.
The PM Framework Applied
PMBOK 6th Edition treats project initiation as a discrete process group containing only two processes: Develop Project Charter (4.1) and Identify Stakeholders (13.1). Done properly, these two transform the CEO's letter into a controlled project.
Step 1: Decompose the brief into SMART objectives
Definition — SMART Objective. Specific, Measurable, Achievable, Relevant, Time-bound. SMART objectives are auditable; aspirational statements are not.
Relationship details
| From | Relationship | To |
|---|---|---|
| Strategic Objective — Secure long-term financial viability — through relocation | leads to | Financial — ≥ A$20M net profit |
| Strategic Objective — Secure long-term financial viability — through relocation | leads to | Schedule — Operational ≤ 18 months — post-closure |
| Strategic Objective — Secure long-term financial viability — through relocation | leads to | Ethics — Zero casualties — Illustrative proposal: ≥ 95% long-term survival |
| Strategic Objective — Secure long-term financial viability — through relocation | leads to | Human — Illustrative proposal: ≥ 80% staff retention |
| Strategic Objective — Secure long-term financial viability — through relocation | leads to | Sustainability — Illustrative proposal: ≥ 60% asset reuse |
Colour coding is deliberate: financial/schedule are business drivers (blue), ethics is a constraint absolute (red), human/sustainability are enabling targets (green). When the inevitable month-9 conflict arises between schedule pressure and animal welfare, the charter has already told you which wins.
Step 2: Log assumptions and constraints explicitly
| Type | Statement |
|---|---|
| Assumption | Current site sells at appraised value within 12 months |
| Assumption | Government grant covers closure-period burn rate |
| Assumption | Crown-land sites are genuinely available in writing |
| Constraint | Zero animal casualties |
| Constraint | 18-month operational deadline |
| Constraint | Reuse existing enclosures where possible |
Assumptions get validated; constraints get managed. Both feed the risk register.
Step 3: Identify stakeholders before drafting authority levels
A first-pass register for the Zoo:
| Stakeholder | Power | Interest | Strategy |
|---|---|---|---|
| Executive Board | High | High | Manage closely; fortnightly reports |
| CEO (sponsor) | High | High | Manage closely; direct line |
| Existing staff | Medium (collective) | High | HR-led engagement plan |
| Site buyer / developer | High | High | Legal interface; manage closely |
| Crown land lessor | High | Medium | Regulatory liaison |
| Environment regulator | High | High | Early engagement |
| Grant funder | Medium | Medium | Reporting compliance |
| Vet / zoological consultants | Medium | High | Expert advisory |
| Construction contractors | Medium | Medium | Contract management |
| Media | High (latent) | Variable | Controlled disclosure |
| Adjacent residents | Medium | Variable | Community consultation |
| Members and visitors | Low individually | Medium | Keep informed |
Step 4: Draft the Charter
The most operationally important section is Section 10 — PM Authority Level. This is where the charter answers: can the PM commit funds without board approval below A$X? Terminate sub-contractors? Authorise change requests up to Y% of budget? The CEO letter is silent on every one of these. The charter must not be.
Step 5: Secure formal authorisation
A charter that has not been signed is a draft, not a charter. Authorisation is what transforms the document from a planning artefact into a legal instrument that grants the PM authority to expend organisational resources.
Relationship details
| From | Relationship | To |
|---|---|---|
| CEO Letter — (Informal) | leads to | Decomposition |
| Decomposition | leads to | Stakeholder Identification |
| Stakeholder Identification | leads to | Draft Charter |
| Draft Charter | leads to | Board Review |
| Board Review | leads to | Authorised Charter v1.0 — (Formal) |
The Result
The PM walks out of the board meeting with three controlled artefacts:
- Project Charter v1.0 — signed, dated, baselined.
- Initial Stakeholder Register — a living document.
- Assumption and Constraint Log — the explicit record of what we believe and what we cannot change.
What the PM does not have, and importantly does not need, is a WBS, schedule, or task-level budget. Those are Phase 2 deliverables.
Core principle. Initiation answers one question: Should this project be authorised, and under whose authority? It does not exist to plan the work.
The Pitfalls
- Treating the letter as the charter. The letter is input, not output.
- Quantifying objectives the sponsor did not quantify. Proposed numbers must be negotiated with the sponsor before being baselined.
- Identifying only friendly stakeholders. The important early identifications are parties with power to say no.
- Drafting authority levels in the abstract. Specify dollar limits and decision categories concretely.
- Skipping the assumption log. Assumptions feel like padding until one fails.
- Forgetting that initiation has its own budget. Decomposition and consultation consume real resources before any deliverable is produced.
Knowledge Check
- The 18-month operational deadline and the "retain existing enclosures where possible" instruction are in tension. Which takes precedence in the charter, and how would you justify this to the board?
- You discover the environment regulator will require a 90-day public consultation on the new site's transport route. Does this belong in the charter, the assumption log, or the risk register?
- Draft a one-sentence PM authority statement that gives decisive authority but preserves board control over commitments above A$500,000.
Key Takeaways
- The CEO letter is input to initiation, not the output. The charter converts qualitative language into quantified, auditable objectives.
- Charter development and stakeholder identification are paired — neither can be completed in isolation.
- Constraints, assumptions, and objectives must be logged separately because they generate different downstream responses.
- The charter's most operationally important section is the PM authority level.
- A charter is not a charter until signed, baselined, and version-controlled.
References
- Project Management Institute 2017, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 6th edn, PMI, Newtown Square, PA.
- Burke, R 2013, Project Management: Planning and Control Techniques, 5th edn, Wiley, Chichester.
- Kerzner, H 2017, Project Management: A Systems Approach, 12th edn, Wiley, Hoboken, NJ.
- Turner, JR 2014, Handbook of Project-Based Management, 4th edn, McGraw-Hill, New York.
- University of South Australia 2015, MPM411 Zoo Relocation Project Brief, UniSA, Adelaide.