KEVOS® Project Delivery Handbook
Carrying Out the Project Work
Planning is intellectual. Execution is visceral. A practical KEVOS handbook for project delivery teams.
In this handbook article
- Why Execution Demands a Different Mindset
- Directing and Managing Project Execution
- What Happens Here
- Performance Reviews
- Developing and Managing the Project Team
- Acquiring the Team
- Motivation Theories in Practice
- Conflict Resolution
- Group Decision-Making
- Managing Project Communications
- The PM as Communication Hub
- Communication Tools and Techniques
- Reporting Guidelines
- Implementing Project Quality Assurance
- Quality Assurance vs. Quality Control
- Conducting Project Procurement
- Contract Administration
- Handling Change Requests from Customers
- Contract Administration Change Requests
- Monitoring and Controlling Project Work
- Integrated Change Control
- The Three Major Causes of Change
- Change Requests — Sources
- Customer Acceptance Testing
- Managing Project Stakeholders
- Phase Review Purpose
- Common Pitfalls
- Key Takeaways
Planning is intellectual. Execution is visceral. This is where the carefully constructed plan meets the messy, unpredictable reality of human teams, shifting priorities, supply chain disruptions, and stakeholder politics.
Lifecycle Phase 3 — Carrying Out the Project Work — is where the majority of project resources are consumed, where the deliverables take physical form, and where the project manager's leadership is tested most severely. It spans two PMBOK Process Groups simultaneously: Executing and Monitoring & Controlling.
Why Execution Demands a Different Mindset
Core Principle: During planning, the project manager is an architect. During execution, they become an air traffic controller — managing multiple moving elements in real time while maintaining situational awareness.
The Executing Process Group integrates people and other resources to carry out the project management plan. But execution without control is chaos. That is why the Monitoring & Controlling Process Group runs in parallel — constantly measuring performance, detecting variances, and triggering corrective action.
Relationship details
| From | Relationship | To |
|---|---|---|
| EXECUTING — Process Group | leads to | MONITORING & — CONTROLLING — Process Group |
| EXECUTING — Process Group | leads to | Direct & Manage — Project Work |
| EXECUTING — Process Group | leads to | Perform Quality — Assurance |
| EXECUTING — Process Group | leads to | Acquire, Develop & — Manage Project Team |
| EXECUTING — Process Group | leads to | Manage — Communications |
| EXECUTING — Process Group | leads to | Conduct — Procurements |
| EXECUTING — Process Group | leads to | Manage Stakeholder — Engagement |
| MONITORING & — CONTROLLING — Process Group | leads to | Monitor & Control — Project Work |
| MONITORING & — CONTROLLING — Process Group | leads to | Perform Integrated — Change Control |
| MONITORING & — CONTROLLING — Process Group | leads to | Validate & Control — Scope |
| MONITORING & — CONTROLLING — Process Group | leads to | Control Schedule, — Costs & Quality |
| MONITORING & — CONTROLLING — Process Group | leads to | Control Risks & — Procurements |
Directing and Managing Project Execution
This is the central execution process — the engine of Phase 3. It involves performing the work defined in the project management plan to achieve the project's objectives.
What Happens Here
- Work is assigned and performed according to the plan
- Deliverables are produced progressively
- Work performance data is collected for analysis
- Change requests are generated when variances are detected
- The project team implements approved changes
Performance Reviews
Definition: Performance reviews are held to assess project status or progress — not to correct the PM's mistakes or to apprise project costs in isolation.
Project performance must be measured at regular intervals to identify variances from the plan. This is not limited to cost or schedule alone — it encompasses all dimensions of project health.
Developing and Managing the Project Team
Acquiring the Team
With the Human Resource Plan from Phase 2 as the guide, the PM now acquires and develops the team.
Motivation Theories in Practice
Two foundational motivation theories directly apply to team management:
Maslow's Hierarchy of Needs (highest to lowest):
Relationship details
| From | Relationship | To |
|---|---|---|
| Self-Actualisation | leads to | Self-Esteem |
| Self-Esteem | leads to | Social / Belonging |
| Social / Belonging | leads to | Security / Safety |
| Security / Safety | leads to | Physiological |
Herzberg's Two-Factor Theory:
| Factor Type | Examples | Effect |
|---|---|---|
| Hygiene Factors (prevent dissatisfaction) | Good supervision, job security, salary, working conditions | Absence causes dissatisfaction; presence does NOT motivate |
| Motivators (drive satisfaction) | Regular promotions, recognition, challenging work, responsibility | Presence creates genuine motivation and engagement |
Exam Tip: Herzberg's motivators include regular promotions and growth opportunities. Good salary, supervision, and job security are hygiene factors — they prevent dissatisfaction but do not drive motivation.
Conflict Resolution
| Method | Description | Long-Term Effectiveness |
|---|---|---|
| Problem Solving / Confronting | Address the root cause directly | Best — resolves the issue permanently |
| Compromising | Both parties give up something | Moderate — partial satisfaction |
| Smoothing / Accommodating | Emphasise agreement, de-emphasise differences | Low — avoids the real issue |
| Forcing | One party imposes their solution | Low — creates resentment |
| Withdrawal / Avoiding | Retreat from the conflict | Seldom resolves the issue — allows a cooling off period but is temporary |
Key Fact: Withdrawal allows a cooling off period but seldom resolves the issue in the long term. Problem solving (confronting) is the most effective method.
Group Decision-Making
Brainstorming encourages team building, analysis of alternatives, and uninhibited verbalization. It does NOT encourage convergent thinking — the entire point of brainstorming is to generate diverse, divergent ideas.
The Delphi Method is best suited for decision-making through structured rounds of anonymous expert input. It is not a cost control or estimation technique.
Managing Project Communications
The PM as Communication Hub
The project manager is the critical element in a project's communication system. They facilitate all project-related communication — upward to sponsors and management, downward to the team, and outward to customers, vendors, and stakeholders.
Communication Tools and Techniques
The major tools and techniques of managing communications include: communication technology, communication models, communication methods, information management systems, and performance reporting.
Reporting Guidelines
| Report Type | Purpose | Use Case |
|---|---|---|
| Progress Report | Status update on current performance | Regular stakeholder updates |
| Formal Project Report | Retrospective analysis of what happened | Post-phase or post-project review |
| Project Office Memo / Directive | Convey planning guidelines and instructions | Team direction and policy |
Exam Tip: A formal project report is the least likely method for explaining project planning guidelines to the team — reports document the past; memos, directives, and meetings convey future direction.
Implementing Project Quality Assurance
Quality assurance is a proactive process — it ensures that the project is using the right processes to meet requirements, not just inspecting deliverables after the fact.
Quality Assurance vs. Quality Control
| Aspect | Quality Assurance (QA) | Quality Control (QC) |
|---|---|---|
| Process Group | Executing | Monitoring & Controlling |
| Focus | Process compliance | Deliverable inspection |
| Approach | Proactive (prevention) | Reactive (detection) |
| Question Answered | "Are we using the right processes?" | "Do the deliverables meet requirements?" |
Conducting Project Procurement
Contract Administration
Effective contract administration requires implementing the contract change control system — not holding bidders conferences (that happens during procurement planning) or developing statements of work.
Handling Change Requests from Customers
When a customer requests a change — even a small one — the project manager must:
- Ask the customer to file a formal change request
- Assess the cost and schedule impact
- Process the request through the change control system
The Golden Rule of Change Management: The impact of every change must be assessed and must go through formal change control — regardless of size, goodwill, or the value of the client relationship.
Contract Administration Change Requests
Contract administration change requests may include modifications to contract terms, termination for unsatisfactory work, modification to product descriptions, and contracted changes. Seller invoices are NOT change requests — they are financial documents.
Monitoring and Controlling Project Work
This process group runs continuously throughout Phase 3, measuring performance against the baseline and triggering corrective action when necessary.
Integrated Change Control
Definition: Perform Integrated Change Control is the process of reviewing all change requests, approving changes, and managing changes to deliverables, organisational process assets, project documents, and the project management plan.
The change control process should include: scope change control, contract administration, quality control, and risk change control. Resource levelling is a scheduling technique, NOT a change control component.
The Three Major Causes of Change
- Errors in the initial assessment of how to achieve project goals
- New information about the project deliverable
- A new mandate (external directive or requirement change)
Relationship details
| From | Relationship | To |
|---|---|---|
| Change Triggers | leads to | Errors in Initial — Assessment |
| Change Triggers | leads to | New Information — About Deliverable |
| Change Triggers | leads to | New Mandate / — External Directive |
| Errors in Initial — Assessment | leads to | Change Request |
| New Information — About Deliverable | leads to | Change Request |
| New Mandate / — External Directive | leads to | Change Request |
| Change Request | leads to | Impact — Assessment |
| Impact — Assessment | Approved | Update Baselines — & Execute |
| Impact — Assessment | Rejected | Document & — Archive |
Change Requests — Sources
Change requests can occur due to:
- An external event such as a change in government regulation
- An error or omission in defining the scope of the product
- An error or omission in defining the scope of the project
All three of these are valid sources. Change requests exist to ensure that the planned outcome of the project is achieved despite evolving circumstances.
Customer Acceptance Testing
When a project meets all product specs, is under budget, and ahead of schedule, but the customer requests changes before acceptance — the correct response is to ask the customer to file a change request. Do not absorb unbudgeted work, bill them later, or refuse outright.
Managing Project Stakeholders
Stakeholder engagement during execution is about maintaining alignment and managing expectations through consistent, strategic communication.
Phase Review Purpose
The purpose of reviewing deliverables and project performance at the conclusion of a project phase is to determine whether the project should continue to the next phase — not to adjust baselines or obtain customer acceptance.
Common Pitfalls
Gold-plating. Adding unrequested features because the project is under budget or ahead of schedule. Every addition carries risk and dilutes focus.
Informal change management. Agreeing to "small" changes without formal documentation creates scope creep — the silent killer of projects.
Neglecting the Monitoring & Controlling parallel. Execution without real-time measurement is flying blind. Performance data must be collected, analysed, and acted upon continuously.
Underestimating communication overhead. Managing communications is not a background task — it is one of eight core executing processes and demands deliberate effort.
Forcing conflict resolution. Forcing creates short-term compliance but long-term resentment. Problem-solving is always the superior approach.
Treating quality assurance as inspection. QA is about process. QC is about product. Confusing the two leads to reactive firefighting instead of proactive prevention.
Key Takeaways
- Phase 3 spans two process groups simultaneously: Executing and Monitoring & Controlling.
- The PM acts as the central communication hub, spending 75–90% of their time communicating.
- Performance reviews assess project status — measure project performance regularly across all dimensions.
- Maslow's hierarchy ranks needs from physiological to self-actualisation. Herzberg's motivators (promotions, recognition) drive satisfaction; hygiene factors only prevent dissatisfaction.
- Withdrawal is the weakest conflict resolution method. Problem-solving is the strongest.
- Every change request must go through formal change control — no exceptions, regardless of size.
- The three major causes of change: initial assessment errors, new information, and new mandates.
- QA (executing, process-focused, proactive) ≠ QC (monitoring, product-focused, reactive).
- Phase reviews determine whether the project should continue to the next phase.